Here's a timeline of the construction progress:

(Click the links below to go directly to a particular section or start with the first link and follow the sublinks which will take you through each page, there's lots of 'em)

6/20/99 Our Basement has been dug, and ready to hold a house!
8/17/99

Our Basement has been layed out with block!

More basement layout pictures!

8/20/99 The basement block structure is filled with concrete and rebar!
9/19/99 The basement cement header is poured, and some wood building materials arrive on site!!

Roof Trusses are delivered and Their first SCREW-UP!

9/28/99 Well, the SCREW-UP is fixed, and they tarred and plastered the basement walls!
10/12/99 Bituthene water barrier is applied to the basement walls!
10/15/99 The floor trusses, no not 2 X 8's, floor trusses, are set in place!!

Basement drains and other boring stuff, might wanna skip this page

10/20/99 Interior Accessories we chose (colors/styles/etc..)
10/23/99 The floor boards are down for the first floor!!
01/02/00 What a MESS!!
01/21/00 The rest of the Building Materials are delivered to the home site!
02/12/00 I Can't Believe My EYES!!
02/17/00 I'm Flabbergasted!! (no pics yet, will update real soon!)
02/26/00 Well, The Electrical Wiring has been run

They also delivered the Windows and Installed the Fireplace.

03/12/2000 Well these 2 pages are not in order like the rest:

The windows are now installed!

I ran all my wires for the phones, computer network, surround sound and cable tv!

03/31/2000 They finally started putting on the brick!!
04/23/2000 They finished the brick!

Now they've started to drywall!

04/05/2000 The Drywall is FINISHED!

Looks like the Hearing and Cooling guys were here too!

04/09/2000 Now they got the Siding up!!!
05/21/2000 They've installed the cabinets!!
05/25/2000 They've Put Our gutters up!!

They put up all the moldings and doors!!

06/02/2000 They've installed the Counter Top's and Sinks!

They finally started covering the inside of the basement walls!

 

 

Page last updated on 6/2//2000